Weekly Update for week commencing 15 March 2021

Foundations/Groundwork.

  •  Substation concrete foundations will start from Monday 15 March.
  • Installation of drainage ongoing.
  • 50mm of Concrete blinding directly to soils below Cellcore continues.
  •  Installation of Cellcore board on going to pour 4 of 4
  • Rebar to pour 4 area on Ground floor slab. (This is to add further strength to concrete).
  • Concreting ground floor slab. Pour 4 of 4 (concrete pour)
  • Installation underground services. (Drainage, BT, Virgin, Electric, Water)
  • Tower crane continues lifting materials to all areas inside site boundary.
  • Temporary decking to First floor slab.
  •  Rebar to first floor slab (This is to add further strength to concrete).
  • Concrete placement to Ground floor slab Pour 1 of 2

 

 

Picture above shows example of concrete pours. This example shows rebar enforcement.

Picture above shows how concrete columns are formed.

Picture above shows the concrete columns once formed.