South Lambeth construction update

Foundations/Groundwork.

  • Excavating of pile caps ongoing
  • Removal of concrete from pile caps by the cropping method ongoing
  • Integrity testing of piles ongoing
  • Installation of ground beams ongoing
  • Installation of drainage ongoing
  • Casting Core B Stair core pile caps
  • Concrete blinding to formation level ongoing
  • Installation of Cellcore board
  • Commencement of Ground floor slab rebar
  • Installation of District heating and underground services