South Lambeth construction update

  • The brickwork will continue rising up from the first floor along the North and South side of the building.  

  • The dryliner will continue to stand walls inside with the metalwork.

  • The scaffolders will be making adaptations to allow the brickwork to progress throughout the week.

  • Our mechanical contractor will continue the main works in the flats once the walls are up.

  • The dryliner will continue the screed operations on the first floor to allow further progression.

  • The windows will be installed on the ground and first floor.

  • The electrician will start the first fix along with the plumbers.

  • There will be deliveries for the plumbers, electricians, dryliners as well as for the bricklayers.

  • We will be working Saturday 8am to 1pm

Picture 1 to show installation of stairs.

Picture 2 to show installation of windows.