04/02/2022
South Lambeth construction update
• Internal blockwork and brickwork ongoing from Level 5 to roof.
• Scaffolding continues in line with brickwork from level 5 upwards.
• Internal partitioning continues on Level 4 and 5.
• Screeding to Level 4.
• Plastering to ground and first floor.
• Decorating to ground floor.
• Kitchens and second fix carpentry to ground floor.
• There will be deliveries for electricians, dryliners and the bricklayers.
• Saturday working will continue for the foreseeable future now internals trades are in progress.