South Lambeth construction update

• The bricklayers will be starting the garden walls on the south elevation.

• The scaffold is now struck on the south elevation. This week, the scaffolders will begin striking the birdcages in the stair cores and scaffold platforms from the fourth to the fifth floors.

• The dryliners will plaster plot A8, the final plot to be plastered. They will start boarding up the walls and instaling ceiling grids in the ground floor communal areas. Making good will continue on the second and third floor maisonettes.

• The electricians will continue the second fixing on the second, third, fourth and fifth floors. Electrical finals will continue on the ground and 1st floors.

• The plumbers have completed all first fixes. The plumbers will continue the second fixing on the second, third, fourth and fifth floors. Fitting radiators etc. Pre-plumbs will continue before fitting kitchens and installing baths on the fourth and fifth floors. They will also start second fixing on the fourth and fifth floors.

• The carpenters will continue the second fixing on the fourth and fifth floors. This includes installing architraves, skirtings, thresholds and kitchens.

• The metal SFS panels on the south elevation continue to be installed on the ground floor. The fourth floor SFS panels are in progress. The 5th floor window heads are now complete.

• There will be deliveries for electricians, plumbers, carpenters, dryliners, and bricklayers. Skip exchanges are scheduled for Monday, Wednesday and Friday.

• The tiler will continue tiling bathrooms and kitchens and grouting.

• Decoration in plots B1 & B2 will continue. The floor layers will continue with the latex on all floors. They will continue laying vinyl after the latex has been rubbed down in the plots that are ready for them.

• The roofers will continue laying the paving slabs on the fourth floor roof.

• From Monday 16 May, we will start the paving works outside the green room on Dorset Road. Temporary hoarding and ramps will be in place from 16 May to direct residents away from the works taking place. Please note: A separate newsletter will be issued with a detailed plan of the routes.

• From Monday 23 May, we will start the planter works outside the entrance to Wimbourne House. Please note: A separate newsletter will be issued in due course with more details of the works.

Picture 1 – Shows latex in plot B7

Picture 2 – Shows carpentry and electrical 2nd fix on the fourth floor