26/11/2021

South Lambeth construction update

·     The brickwork will continue rising up from the third floor going around the perimeter of the building.

·      The scaffolders will be making adaptations to allow the brickwork to progress throughout week.

·     Our mechanical contractor will be installing the plant room and the pipework for the flats on level 1

·     The dryliner will start standing the walls on the second floor

·      The windows will finish on the second floor.

·     The electricians will continue wiring the first floor

·      The screed will finish on the second floor

·     There will be deliveries for the plumbers, electricians, dryliners as well as for the bricklayers.

·      We will be working Saturday 8am to 1pm

Picture 1 to show level one wall setting out.  

Picture 2 to show progress on level two screed prep