25/03/2022

South Lambeth construction update

• The bricklayers have now completed all brickwork and will concentrate on snagging and remedial works.

• We will start taking down the scaffolding on the north and west elevations on Monday 28 March.

• The dryliners will continue closing up plots on the second and third floors ready for plaster. They will complete all 2nd-floor plots plastered by the end of the week. They will also start closing up plots on the fourth and fifth floors. They will also start boarding the walls and ceilings in the communal areas.

• The electricians will continue the first stage of fixing in the fourth-floor maisonettes. They will also continue to the second stage of fixing and testing on the ground and first floors. They will start the second fixing on the second and third floors. Communal wiring will continue through the risers.

• The plumbers will continue the first stage of fixing on the fourth and fifth floors. The sprinkler installers will second stage of fixing on the second/third floors and the first fixing stage on the fourth and fifth floors. Pre-plumbs will continue before the fitting of the kitchens and installation of baths to the first floor.

• The carpenters will continue the second fixing stage on the second and third floors. This involves installing skirtings, stair banisters, kitchens, and hanging doors. They will complete the installation of all front entrance doors. They will also start the second stage of fixing on the fourth and fifth floors once mist coated.

• The roof parapet cappings will continue on the fourth floor.

• Window installations will continue on the fifth floor.

• There will be deliveries for electricians, plumbers, carpenters, dryliners as well as for the bricklayers. Skip exchanges are scheduled for Monday, Wednesday and Friday.

• The lightening protection will be completed on the level six roof.

• The tiler will continue tiling bathrooms and kitchens, and grouting.

• Saturday working will continue until further notice.

• The tower crane will be dismantled on Thursday 31 March 2022.

Picture 1 – Shows level 2 walkway waterproofing

Picture 2 – Shows second fix carpentry in plot B4 complete