South Lambeth construction update

• The brickwork will continue rising up from the second floor going around the perimeter of the building.

• The screeding will start on the first floor.

• The scaffolders will be making adaptations to allow the brickwork to progress throughout week.

• Our mechanical contractor will continue the main works in the flats once the walls are up.

• The dryliners will continue the parge coat works on the second floor.

• The windows will be installed on the first floor.

• The electrician will start the first fix along with the plumbers.

• There will be deliveries for the plumbers, electricians, dryliners as well as for the bricklayers.

• We will be working Saturday 8am to 1pm

Picture 1 to show install of lift.

Picture 2 to show progression of window install.