  • South Lambeth construction update

21/01/2022

South Lambeth construction update

• The bricklayers will continue with the fourth and fifth floor brickwork on the North and East elevations. They will continue with the brick piers on the fourth floor South elevation.

• The scaffolders will be adapting the brickwork on the North and South elevations to allow for the brickwork to be built to full height.

• The dryliners will continue first fixing on the third floor. They will also be plastering water and heating cupboards inside the first floor plots. There will be screeders coming next week for the fourth floor.

• The electricians will continue first fixing in second floor maisonettes and third floor plots and continue wiring in the communal areas.

• The plumbers will continue first fixing on the second floor. The sprinkler installers will be completing the ground floor sprinkler systems.

• The carpenters will be returning to install the final timber stairs in the fourth to fifth floor maisonettes.

• There will be deliveries for electricians, dryliners as well as for the bricklayers.

• We will recommence Saturday working from 29 January 2022.

Picture 1 to show electrical first fix on the third floor

Picture 2 to show North elevation brickwork progress