South Lambeth construction update

The bricklayers will continue with the garden walls on the south elevation throughout the week.

• The dryliners will continue first fixing in the ground floor communal areas. They will continue making good in the second and third floor maisonettes. They will continue building bathroom vanity boxes in the fourth and fifth floor maisonettes. They will start closing up the bathrooms in the accessible plots.

• The electricians will continue the second fixing on fourth and fifth floors. Electrical finals will continue on the ground and first floors, and commence on the second and third floors. Communal wiring will also continue.

• The plumbers will continue the second fixing on the fourth and fifth floors. Fitting radiators etc. Pre-plumbs and second fixes will continue before fitting kitchens and installing baths on the fourth and fifth floors. They will also continue with the bathroom adaptions in the accessible plots.

• The carpenters will continue the second fixing on the fourth and fifth floors. This will include installing architraves, skirtings, thresholds and kitchens. They will also be completing finals on the first floor. This will include fitting ironmongery, toilet roll holders etc.

• There will be deliveries for electricians, plumbers, carpenters, dryliners, and bricklayers. Skip exchanges are scheduled for Monday, Wednesday and Friday.

• The tiler will continue tiling bathrooms and kitchens and grouting.

• The floor layers will start latexing the fourth and fifth floors. They will continue laying vinyl after the latex has been rubbed down in the plots that are ready for them.

• The roofers will continue laying the paving slabs on the fourth floor roof. They will also begin waterproofing the fourth floor walkway.

• Neos (our door contractor) will return to install the internal communal doors on the ground floor in core A.

• The utility connection works on Cobbett Street will continue through to Friday 3rd June.

Please note: The new site hoarding layout and paving works outside Wimborne House will begin on Monday 23rd May

Picture 1 – Shows vinyl flooring installation in progress

Picture 2 – Shows fourth floor bathroom tiling in progress