South Lambeth construction update

·     The brickwork will continue rising up from the third floor going around the perimeter of the building.

·      The scaffolders will be making adaptations to allow the brickwork to progress throughout the week.

·     Our mechanical contractor will be installing the plant room and the pipework for the flats on level 1

·     The dryliner will finish standing the walls on the first floor

·      The windows will finish on the second floor.

·     The electricians will continue wiring the first floor

·      The balcony railings will continue on the second floor.

·     There will be deliveries for the plumbers, electricians, dryliners as well as for the bricklayers.

·      We will be working Saturday 8am to 1pm

Picture 1 to show level 1 balcony railing install.

Picture 2 to show progress on level one with first fixing.