South Lambeth construction update

• The brickwork will continue rising up from the second floor going around the perimeter of the building.

• The dryliner will finish the standing of walls inside with the metalwork.

• The scaffolders will be making adaptations to allow the brickwork to progress throughout week.

• Our mechanical contractor will continue the main works in the flats once the walls are up.

• The dryliner will continue the screed preparations on the first floor to allow further progression.

• The windows will continue to be installed on the ground and first floor.

• The electrician will start the first fix along with the plumbers.

• There will be deliveries for the plumbers, electricians, dryliners as well as for the bricklayers.

• We will be working Saturday 8am-1pm

Pictures to show installation of first fix plasterboard and progression