  • South Lambeth construction update

11/12/2021

South Lambeth construction update

• The brickwork will continue rising up from the third floor going around the perimeter of the building.

• The hand rail will continue to be installed in the main stair cores.

• The scaffolders will be making adaptations to allow the brickwork to progress throughout week.

• Our mechanical contractor will be installing the plant room and the pipework for the water tank

• The dryliner will finish standing the walls on the first floor

• The windows will start on the second floor.

• The roofers will finish the balcony on the first floor.

• There will be deliveries for the plumbers, electricians, dryliners as well as for the bricklayers.

• We will be working Saturday 8am to 1pm

Picture 1 to show completed bio diversity roof .

Picture 2 to show progress on level 1 balcony terrace