South Lambeth construction update

• The brickwork will continue rising up from the third floor going around the perimeter of the building.

• The scaffolders will be making adaptations to allow the brickwork to progress throughout week.

• Our mechanical contractor will be installing the plant room and the pipework for the flats on level 1

• The dryliner will start standing the walls on the third floor

• The windows will start on the third floor.

• The electricians will continue wiring the first floor

• The screed will finish on the second floor

• There will be deliveries for the plumbers, electricians, dryliners as well as for the bricklayers.

• We will be working Saturday 8am to 1pm

Picture 1 to show level 2 standing of walls

Picture 2 to show ground floor ready for close up.